Pavement showing significant surface deterioration with moderate cracking patterns. Structural integrity is declining—this is the critical decision point for rehabilitation versus continued decline.
Structural overlay or rehabilitation required. Surface treatments alone will not be effective at this stage. A 2-3 inch asphalt overlay after crack repair is the typical treatment. Delaying action will accelerate deterioration to the point where full reconstruction is needed.
Mill and overlay (2"): $15-25/sq yd. Cold-in-place recycling with overlay: $12-20/sq yd. Acting at PASER 5 costs roughly one-third of what full reconstruction will cost if the road is allowed to deteriorate to PASER 2-3.